Aguas de Calpe is carrying out rehabilitation works on the sewage pumping station in Avenida del Port. The cost of the works is 80,754.55 € and the duration of the works will be two months.
This action completes the sewerage network of the access area to the fishing port after the collapse of a section of the collector recorded last March.
The rehabilitation works consist of adapting the connections of the four inlet collectors to the pumping station by building a new pumping chamber. This will require the demolition of the current cottage.
The difficulty of the works lies in the fact that the works will be carried out in the same place as the existing installation, maintaining the sewerage system and with excavation depths of more than three meters.
The works include the relocation of the four inlet headers to the pumping station and their diversion using a Godwin pump to maintain the sewerage in the area while the works are carried out. In addition to the subsequent dismantling and removal of the existing electromechanical equipment, demolition of the existing pump shaft and ceiling and construction of the new pump shaft and shed with identical dimensions to the original.